Agile KS 3 – Control Limits for Agile projects – PMI-ACP Exam

Agile KS 3 – Control Limits for Agile projects – PMI-ACP Exam

 

By plotting the time to delivery / velocity / escaped defects / etc. as a control chart

If some data fall outside the upper / lower control limits, a root cause analysis should be performed to rectify the issue

  • Common cause – systematic issue, need to be dealt with through trend analysis
  • Special cause – happens once only due to special reasons

Another example is the WIP limit in Kanban boards

 

See more: Control Charts and Control limit vs Specification Limit