PMP Quy Trình Estimate Activity Durations 6.4
Process Name: Estimate Activity Durations

Process Group: P

Approximating the number of work periods needs to complete individual activities with estimated resources.

=> DURATION: the total number of work periods (not including holidays or other nonworking periods) requires to complete a schedule activity or WBS component. Usually expressed as work days, workweeks. Constrast with effort.

Input
Tool/Techniques
Output
1. Project management plan
Schedule Mgmt Plan

2. Project documents
Activity List

Activities Attributes

- Resource Calendars

Risk Register
Assumption log
LL register
Milestone list
– Project team assignments
RBS
Resource requirements
Risk Register
7. EEF

8. OPA
1. Expert Judgment

2. Data analysis
Alternative Analysis

Reserve analysis
3. Analogous estimating
4. Parametric estimating
5. Three-point estimating

6. Bottom-up Estimating

7. Decision making
8. Meetings
1. Duration estimates

2. Basis of estimates
3. Project documents updates
Activity attributes
Activity list
Assumption log
LL register
PMP Process Groups Map: https://hocpmp.com/itto

Leave a Reply

Tôi rất vui khi bạn đã quyết định để lại comment, tôi sẽ phản hồi tất cả các comment nhanh nhất khi có thể. Chú ý tất cả comment đều được kiểm duyệt cẩn thận, xin đừng cố gắng spam hoặc quảng cáo. Xin cảm ơn.

This site uses Akismet to reduce spam. Learn how your comment data is processed.