PMP Quy trình Estimate Activity Resources 9.2
Process Name: Estimate Activity Resources (9.2)

Process Group: P

Estimating the type and quantities of material, people, equipment, or supplies required to perform each activity.

=> RESOURCES: skilled human resources (specific disciplines either individually or in crews or teams), equipment, services, supplies, commodities, material, budgets, or funds.

Input
Tool/Techniques
Output
1. Project management plan
Resource management plan
Scope baseline
2. Project documents
Activity List

Activities Attributes

- Resource Calendars

Risk Register
Assumption log
Cost estimates
Resource requirements
3. EEF

4. OPA
1. Expert Judgment

2. Data analysis
– Alternatives
3. Analogous estimating
4. Parametric estimating

5. Bottom-up Estimating

6. PMIS
7. Meetings
1. Resource requirements

2. Basis of estimates
3. Resource Breakdown Structure
3. Project documents updates
Activity attributes
Assumption log
LL register
PMP Process Groups Map: https://hocpmp.com/itto

Leave a Reply

Tôi rất vui khi bạn đã quyết định để lại comment, tôi sẽ phản hồi tất cả các comment nhanh nhất khi có thể. Chú ý tất cả comment đều được kiểm duyệt cẩn thận, xin đừng cố gắng spam hoặc quảng cáo. Xin cảm ơn.

This site uses Akismet to reduce spam. Learn how your comment data is processed.